View Single Post
 
Old 05-31-2016, 10:14 AM
cookieburk cookieburk is offline Windows 8 Office 2013
Novice
 
Join Date: May 2016
Posts: 4
cookieburk is on a distinguished road
Default Project Late Status Changes from One User to Another

MS Project 2010 Pro Standalone. I have a project file that has three late tasks. Of the three tasks, one is 60% complete, a duration of 77 days, start date 3/21/16 and end date of 7/7/16. Status date is 5/24/16; calendar is US and Federal Holidays. When I send this project file to a colleague this task is shown as on schedule. We have verified the status date and calendar in my colleague's MS Project. Any ideas on why/how the late calculation is different?
Reply With Quote