Total Slack Calculation Incorrect in SubProjects vs MasterPlan
View Single Post
05-31-2016, 04:01 AM
ana
Windows 7 32bit
Office 2010 32bit
Novice
Join Date: May 2016
Posts: 2
Hi Julie,
thank you for your reply.
I have a constraint in Sub - Project B, however I don't see why the negative slack wouldn't appear in project A anyway, since the activities in this file are preceding Project B.
ana