View Single Post
 
Old 09-09-2010, 01:05 PM
duraid duraid is offline Windows Vista Office 2007
Novice
 
Join Date: Sep 2010
Posts: 2
duraid is on a distinguished road
Unhappy how to make fields calculation variable according to the filter i use

Hi all!
Can you help me with this problem?
I have a daily production plan and for each part there is an area.
I have made a field in MS project called area and i insert the area manually.
What I need is to make MS project calculate the area automatically according to the date range I choose in the filter. (In other word i need ms project change the calculation according to the filter)
For the moment when I can't read the real daily area, because what I get always is the total area for the project.
Reply With Quote