Okay so I simplified it a little bit like you both suggested - I'm very new to Project so I'm still learning how all of the automatic stuff works. one thing I cant figure out is why I don't have the option to display the "start" and "finish" on the gantt chart. I have the option to display the custom starts and finishes but not the standard ones.

any ideas?

Thanks
Double click on a blank area of the gantt chart and you have access to all the types of bar which display. Chose the one called "task" and then go down to the bottom where it says "text" and type start in the left and finish in the right box.
Regards
Miles