Default Task type relationships not acting as expected

I've gone through the MS tutorials on the relationships between effort driven, fixed duration, fixed work, and fixed units but there's something that does not appear to be acting right. I've got my tasks set for fixed work. But the summary task shows up as fixed duration and cannot be changed. When I now change the end date of a task, the start date moves with it, keeping my resource units at 100%, even though my tasks are marked to start as soon as possible. In effect, I'm trying to set up a two week task (duration) witn only 20 hrs of work spread across those two weeks.

What's the easiest way to set up a lot of tasks such that my work stays at what I set it and I can change the durations? I thought fixed work would do it, but there must be another switch somewhere that I missed. Either that or the order I do things is affecting how Project handles it.

Thanks.
Reply With Quote
Reply

Bookmarks

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
How to enlarge type size on screen? Marianne126 Word 0 04-10-2007 11:13 AM
Outlook 2003 Task Reminders jcnansen Outlook 0 07-26-2006 04:34 PM
Task Problem scotthutchings Outlook 0 07-03-2006 08:08 PM
OL 2003 Cannot save a new task rene Outlook 2 06-13-2006 12:07 PM
"outlook task" bmccuskee Outlook 2 11-29-2005 12:40 AM


All times are GMT -4. The time now is 04:07 PM.


Powered by vBulletin® Version 3.8.1
Copyright ©2000 - 2010, Jelsoft Enterprises Ltd.
SEO by vBSEO 3.3.2 ©2009, Crawlability, Inc.