Microsoft Office Forums

Go Back   Microsoft Office Forums > Microsoft Office > Project

Reply
 
LinkBack Thread Tools Display Modes
  #1  
Old 03-07-2019, 02:37 AM
jraward jraward is offline Windows 7 64bit Office 2016
Novice
 
Join Date: Mar 2019
Posts: 1
jraward is on a distinguished road
Default Swimlane view with Accountable channels and Responsible tasks

I'm trying to create a swimlane that groups together the tasks that each sub project manager is Accountable for delivering, whilst also assigning individual Responsible resources that are split across all tasks regardless of who is overseeing it (Accountable):




I've tried using 'Group' to nest them, however a Resource can only belong to a single Group and we need resources to be supervised by different PMs through the project life (line set up is initially specified by engineer, then later in the project it will be installed by lead ops):


What options do I have?
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Sorting in Advanced View in Tasks onmytenthlife Outlook 0 07-31-2018 05:54 AM
Creating task view of open tasks rjpiekos Project 1 01-23-2015 08:00 PM
Outlook Tasks 'current view'? markg2 Outlook 0 07-27-2014 08:10 AM
Inactive tasks and resource usage view codeghi Project 1 05-05-2014 06:59 AM
Missing Tasks from Network Diagram View OTPM Project 3 11-20-2012 03:37 PM


All times are GMT -7. The time now is 12:03 AM.


Powered by vBulletin® Version 3.8.1
Copyright ©2000 - 2019, Jelsoft Enterprises Ltd.
SEO by vBSEO ©2011, Crawlability, Inc.
MSOfficeForums.com is not affiliated with Microsoft