Hi


Is there a way to change the Status indicator for late tasks to only show as late if past the finish time of the item




Or is there another way to indicate overdue tasks on the Gantt chart


Sorry very new at this. Using Project 2016



Thnx
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Status Date in a Report ebilbrough Project 3 03-09-2017 09:45 AM
Project Late Status Changes from One User to Another cookieburk Project 4 06-01-2016 12:31 PM
Project Status and Late Tasks - Incorrect BarryB Project 4 08-02-2015 01:50 PM
Meaning of current date vs status date when saving baselines ketanco Project 1 02-08-2012 02:20 PM
Checking ref # status based on sheet2 ref #. aligahk06 Excel 1 04-26-2010 11:22 PM


All times are GMT -7. The time now is 08:41 AM.


Powered by vBulletin® Version 3.8.1
Copyright ©2000 - 2018, Jelsoft Enterprises Ltd.
SEO by vBSEO ©2011, Crawlability, Inc.
MSOfficeForums.com is not affiliated with Microsoft