#1
|
|||
|
|||
Updating an activity
I'm a PM, and I'm trying to use Project to optimize my EV analisys. I'm involved into a construction project, and I want to use a simple example to explain my doubt.
First I summarize main data: activity excavation estimated q.ty 300m3 duration 30 days Amount 1000 € I fixed a baseline, and then I put the next status date after 15 days. Project would consider a BWCS of 500 € (considering a quantity of 150 m3). But on site, at that status date, I've measured 240 m3 of excavation. So I should update the activity at 80 % (and not on 50%), and put an actual cost of 800 €, shouldn't I? |
#2
|
|||
|
|||
Anyone can reply?
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
critical activity with floating end date | ketanco | Project | 7 | 06-17-2014 10:17 AM |
activity id number showing together with activity name | ketanco | Project | 1 | 04-08-2014 01:27 PM |
tying to a critical activity | ketanco | Project | 1 | 08-04-2012 05:59 AM |
changing one activity in a baseline | ketanco | Project | 5 | 02-11-2012 07:24 AM |
updating a delayed activity | ketanco | Project | 3 | 01-26-2012 01:47 PM |