Hello,


I use a lot the command "inactive tasks" which permits me to reschedule the project so that all subsequent tasks are moved forward based on the “removal” of the inactive tasks.
But if a task has a precedessor with lag time and you try to inactive it, it seems that the next task "feels" this lag and is not rescheduled.
I attached an example file: if you try to inactive the task "E", task F doesn't follow the end of task D as I would like.
How can I resolve it?
Regards
Codeghi
Attached Files
File Type: mpp problem.mpp (230.5 KB, 0 views)
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Save and Close powerpoint if it is inactive MetteGaga PowerPoint 0 04-16-2015 05:14 AM
ZOOM and SCROLL of Inactive Window exceere Excel Programming 2 07-09-2014 02:33 AM
Copy and Paste of a Task...Including all of the Task's 'children'...to a new task KRTSTARRYNIGHT Project 1 07-01-2014 06:54 AM
Finding the Selection in an inactive worksheet BobBridges Excel Programming 4 09-30-2013 02:03 PM
Options Buttons become inactive clint Word 0 02-25-2010 04:31 PM


All times are GMT -7. The time now is 07:08 AM.


Powered by vBulletin® Version 3.8.1
Copyright ©2000 - 2018, Jelsoft Enterprises Ltd.
SEO by vBSEO ©2011, Crawlability, Inc.
MSOfficeForums.com is not affiliated with Microsoft