Default Microsoft Project Extened Working Hours with overtime

Hi All,

I'm new to Microsoft Project and this forum. Would appreciate some help with the below as I'm totally stuck on this one.

Say I have project with many different types of resources. The standard working week is 40 hours a week. Lets say I want to change the working week to 50 hours, however 10 hours is to be assigned to to overtime.



I've already assigned the overtime rate, and I'm well aware of task usage tab. However I cant really find a practical way to do the above, any suggestions on how this can be done?

Thanks,
Reply With Quote
Reply
Please reply to this thread with any new information or opinions.

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Overtime after 40 hours tasha2515 Excel 6 08-05-2017 08:39 AM
Microsoft Project Server, Microsoft Project Online and Project Web App - Whats the difference? chocolateCupcakes Project 1 02-11-2017 12:25 PM
Project Calendar - working days have varying hours BarryB Project 1 11-30-2016 07:36 AM
about usage of Timesheet and Overtime in Project server Hyung-Ho Yoon Project 3 07-15-2014 09:13 AM
Project Hours Mav Project 4 03-07-2014 04:47 PM


All times are GMT -7. The time now is 03:17 PM.


Powered by vBulletin® Version 3.8.1
Copyright ©2000 - 2017, Jelsoft Enterprises Ltd.
SEO by vBSEO ©2011, Crawlability, Inc.
MSOfficeForums.com is not affiliated with Microsoft