Default Project Calendar for Shutdowns / Turnaround


I am using MS Project 2016 for Planning of Shutdown of 15 Maintenance Days having Calendar of 24/7.

I have developed resource sheet in MS Project 2016 but I want to know what calendar shall I use as a base for Resources as labors used in day and night shifts having same craftsmanship but their quantities will be different in both shifts.

I can be contacted at engr.ahsanbaig@gmail.com.
Reply With Quote
Reply
Please reply to this thread with any new information or opinions.

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
MS Project import contacts with their calendar Simon_0705 Project 0 05-08-2017 05:44 AM
URGENT PLEASE: Project Calendar company holidays BarryB Project 2 09-17-2016 09:35 AM
Setting a default project calendar raminraiszadeh Project 4 03-24-2016 06:23 AM
2 Shift - Project Calendar Mav Project 1 09-08-2014 10:42 AM
How can I use persian (solar) calendar in ms project 2010? mammadkoma Project 0 11-13-2010 06:01 AM


All times are GMT -7. The time now is 09:32 AM.


Powered by vBulletin® Version 3.8.1
Copyright ©2000 - 2017, Jelsoft Enterprises Ltd.
SEO by vBSEO ©2011, Crawlability, Inc.
MSOfficeForums.com is not affiliated with Microsoft