I need to create a report that shows “work” or “remaining work” across time at a resource group level. The visual report works correctly on each individual project (as per image 1). I have created a master template & assigned several sub projects to this.

However when trying to view the cumulative hours across a resource group across sub projects in a master, I am unable to create the report when filtered on the relevant level. (image 3)
The number of hours that appears in the field “Remaining Work” is correct at a Resource Group level – ie – it adds the hours per resource within the relevant resource group. Plus when broken down a resource level, the hrs are shown (image 2)

However when I filter this over time, at a group level no hours are calculated?

I have tried using a Resource Pool & by just using a master Document & copying the resource names each time, so the naming conventions are common, both show the correct figures, but when they are filtered at a task level in the sub project version – the data is blank?

Thank you for your help
Attached Images
File Type: jpg Image 1.JPG (83.2 KB, 9 views)
File Type: jpg Image 2.JPG (87.4 KB, 9 views)
File Type: jpg Image 3.JPG (101.3 KB, 9 views)
Reply With Quote
  #2  
Old 02-21-2017, 10:57 AM
JulieS JulieS is offline Windows 10 Office 2016
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,696
JulieS will become famous soon enough
Default

Is the resource pool connnect to the subproject? If you are using a pool, it needs to be connected to the subproject files and not the master project. You should be reporting from the Resource Pool file.
Reply With Quote
  #3  
Old 02-22-2017, 06:34 AM
RichB RichB is offline Windows 10 Office 2016
Novice
 
Join Date: Feb 2017
Posts: 2
RichB is on a distinguished road
Default

yes the resource pools are linked, but I wasn't running the report from the Resource Pool. I was running from the master doc, so I think that has done it!

Thank you for your help
Reply With Quote
  #4  
Old 02-24-2017, 08:55 AM
JulieS JulieS is offline Windows 10 Office 2016
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,696
JulieS will become famous soon enough
Default

Great. Let us know if you have any further questions.
Reply With Quote
Reply

Tags
resource groups, sub projects

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Fixed Hours for Resource Planning ebilbrough Project 1 12-28-2016 11:47 AM
Project 2013 - Issue with Resource Usage showing wrong dates michaelwex Project 1 02-11-2016 08:41 AM
Seperate Cost per Resource Group and Taskname Emanol Espina Project 6 12-17-2015 02:59 PM
Resource not getting enough hours allocated to them, therefore extending duration joday48 Project 1 08-01-2014 08:54 AM
Gantt bar text labels - possible to put resource hours against the bars? mtbtomo Project 5 05-14-2014 01:18 PM


All times are GMT -7. The time now is 10:14 PM.


Powered by vBulletin® Version 3.8.1
Copyright ©2000 - 2018, Jelsoft Enterprises Ltd.
SEO by vBSEO ©2011, Crawlability, Inc.
MSOfficeForums.com is not affiliated with Microsoft