#1
|
|||
|
|||
Copy resource usage to excel
Hi All,
I hope this finds everyone well. Im trying to copy the resource usage data from MSP into Excel. Im sure this used to be a simple copy and paste exercise but clearly Microsoft have simplified it further into a long winded, complicated way. I understand that I can use a report for this but I really want it minute by minute so that I can do further calculations. Ideally it will have hours and minutes along the top and the resource or task down the left. Under the appropriate time it will just have a "1m" under it as per projects resource usage sheet. Does anyone know how to do this? Thanks Alex |
#2
|
|||
|
|||
I'm afraid your best choice is going to either be copy/paste or export through VBA. The visual reports do not go down to minute/hour level.
|
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Resource Usage View - Is it possible to display resource names | Andrea Schanz | Project | 6 | 09-22-2014 07:47 AM |
Resource Usage View | bumpui | Project | 7 | 06-18-2014 05:32 AM |
Exporting Resource Usage data to Excel | samg54 | Project | 1 | 08-02-2013 05:28 AM |
project 2010 resource usage | runejors | Project | 1 | 04-04-2013 05:55 AM |
MS Project - Resource usage printout | scrinmemphis | Project | 1 | 02-22-2013 02:30 PM |