codeghi codeghi is offline Team Planner view with 0% assignment Windows 7 64bit Team Planner view with 0% assignment Office 2010 64bit
Advanced Beginner
Team Planner view with 0% assignment
 
Join Date: Jan 2010
Posts: 38
codeghi is on a distinguished road
Default Team Planner view with 0% assignment

Hello,


I have a project file (v. 2010) with a resourcing pool, so my preferred view is the "Team Planner" one.
I have this problem: there are some tasks that have resources with a unit assignment of 0%, but in these cases, the "Team Planner" view doesn't show anything!
How can I visualize the task for a resource that has 0% units assignment in the "Team Planner" view?
Regards, codeghi
Reply With Quote
  #2  
Old 04-25-2015, 09:23 AM
codeghi codeghi is offline Team Planner view with 0% assignment Windows 7 64bit Team Planner view with 0% assignment Office 2010 64bit
Advanced Beginner
Team Planner view with 0% assignment
 
Join Date: Jan 2010
Posts: 38
codeghi is on a distinguished road
Default

Sorry, I must clarify the question.
The task is common to two resources: resource A with 100% unit, resource B with 0% unit, the task's duration is 5 days for example.
In the "Team Planner" view I can see the task for resource A, but I cannot see the same thing for resource B: how can I do this?
Reply With Quote
  #3  
Old 04-27-2015, 03:09 PM
JulieS JulieS is offline Team Planner view with 0% assignment Windows 7 64bit Team Planner view with 0% assignment Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Resources assigned to tasks with zero percent assignment units does not calculate work. My guess is, that is why they do not show the assignment in the Team Planner view.

Why do you have resources assigned at 0% assignment unit? The assignment does show in the Resource Usage view.
Reply With Quote
  #4  
Old 04-29-2015, 07:15 AM
codeghi codeghi is offline Team Planner view with 0% assignment Windows 7 64bit Team Planner view with 0% assignment Office 2010 64bit
Advanced Beginner
Team Planner view with 0% assignment
 
Join Date: Jan 2010
Posts: 38
codeghi is on a distinguished road
Default

Hello, this is the problem: I have a "material" resource assigned to 100% for a task A, and a "work" resource assigned to 0% to perform the task A, and at the same time assigned to 100% for the task B.
My wish is visualize in the "Team Planner" view that "work" resource will be occupied for both the tasks
Reply With Quote
  #5  
Old 04-29-2015, 08:22 AM
JulieS JulieS is offline Team Planner view with 0% assignment Windows 7 64bit Team Planner view with 0% assignment Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Material resources as set out by Project do not have assignment units. You can change the type of the material resource to Material - but it sounds like your "material" resource is a work resource.

Work resources perform work - not material resources. It sounds like you have things backwards. If Resource A is performing the task, they cannot be assigned at 0%.

Please tell me why you are doing what you are doing. I understand you wish to see that the work resource is assigned to both tasks in team planner - but with zero assignment units, that is not going to happen. The Team Planner view shows you work resources who are assigned to tasks and have a work value.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Team Planner view with 0% assignment Why do my Resources have different Project Start Dates in Team Planner ? AmmeLane Project 1 06-06-2014 06:42 AM
Team Planner view with 0% assignment Formatting External Tasks in Team Planner steve086 Project 3 01-10-2014 03:11 PM
Refining Team Planner View in MS Project 2010 CarolinaGamecock Project 1 11-27-2013 12:18 PM
Team Planner view with 0% assignment How to Improve task Detail in Team Planner ? Tray Project 9 07-07-2013 03:44 PM
Team Planner view with 0% assignment Team Planner-maintaining accuracy in task start and finish times david_23 Project 9 04-19-2012 08:33 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:08 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft