Issue regarding calculating costs of rental equipment
Hello and good afternoon sirs and madams,
I have a specific issue regarding a material resource. It might seem a bit dumb but i just started my Master in Project Management and these days are marking my first encounters in MS Project. Describing the issue: We (a friend and i) were assigned to plan a project for a complete maintenance of an Oil Refinery . In some of the tasks i have to assign a material resource ( a crane to be exact) . The Crane's cost is 400e/day . Our problem is this , we are trying to make this dynamic(for task duration changes) . For example . In the 1st summary task the crane is being used for 22 hours , and in the second 13 hours . We want to assign the Material crane resource to calculate the exact cost per days (f.e. if total 1.3 per summary task to calculate the cost of the crane 2x400 ). I hope you peeps got what i mean, and the help will be very appreciated , because we are really stuck trying to program this with durations on excel and nothing seems to solve the puzzle Thank you D |
#2
|
|||
|
|||
You may assign material resources at a specific unit per day.
If the duration of the task increases or decreases, Project will calculate the correct usage of the crane. I hope this helps. |
#3
|
|||
|
|||
Thank you for your help .
I used the same method little before i saw your post , but it would have really helped if i hadnt figure it out. Appreciate your answer Cheers |
#4
|
|||
|
|||
You're welcome. You'll likely remember it longer as you had to search it out.
|
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
a rental period in between two activities | ketanco | Project | 5 | 10-21-2012 06:28 AM |
assiging equipment as resource | ketanco | Project | 3 | 06-10-2012 03:32 AM |
Non-recurring costs (NRE) | Trigger | Project | 1 | 04-26-2012 03:41 PM |
Managing equipment and person operating equipment | ProfessorGilligan1 | Project | 1 | 04-12-2012 12:29 PM |
entering lump sum costs | ketanco | Project | 1 | 12-24-2011 12:56 PM |