Hello, in Project 2010 I often use the inactive task feature that allows me to model changes faster without destroying the project schedule.
But there is a problem: when I apply the "Resource Usage view" and create a group that groups by name and then by project, MS Project continues to calculate the inactive tasks as work effective tasks.
How could I fix it?
codeghi is offline   Reply With Quote
Old 05-05-2014, 06:59 AM   #2
Join Date: Dec 2011
Location: New England
Posts: 1,696
JulieS will become famous soon enough

I see the same issue. The "Project" group is not showing the correct data. I'd say it is a bug and I'm afraid I don't know how to fix it. I'll play around for a bit to see if I can come up with a solution.
The resource usage view without grouping show the correct data - it is somehow the group header that causes the issue.
Julie Sheets
Microsoft Project MVP
JulieS is offline   Reply With Quote

Thread Tools
Display Modes

Similar Threads
Thread Thread Starter Forum Replies Last Post
Resource Usage view does not correctly export to a Visual Report cergon Project 3 04-25-2014 06:10 AM
Exporting Resource Usage data to Excel samg54 Project 1 08-02-2013 05:28 AM
project 2010 resource usage runejors Project 1 04-04-2013 05:55 AM
MS Project - Resource usage printout scrinmemphis Project 1 02-22-2013 02:30 PM
Resource Usage sheet - options Andy Bain Project 1 11-05-2010 12:42 PM

All times are GMT -7. The time now is 12:07 AM.

Powered by vBulletin® Version 3.8.1
Copyright ©2000 - 2018, Jelsoft Enterprises Ltd.
SEO by vBSEO ©2011, Crawlability, Inc. is not affiliated with Microsoft