Default Inactive tasks and resource usage view


Hello, in Project 2010 I often use the inactive task feature that allows me to model changes faster without destroying the project schedule.
But there is a problem: when I apply the "Resource Usage view" and create a group that groups by name and then by project, MS Project continues to calculate the inactive tasks as work effective tasks.
How could I fix it?
Reply With Quote
  #2  
Old 05-05-2014, 06:59 AM
JulieS JulieS is offline Windows 7 64bit Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,696
JulieS will become famous soon enough
Default

I see the same issue. The "Project" group is not showing the correct data. I'd say it is a bug and I'm afraid I don't know how to fix it. I'll play around for a bit to see if I can come up with a solution.
The resource usage view without grouping show the correct data - it is somehow the group header that causes the issue.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Resource Usage view does not correctly export to a Visual Report cergon Project 3 04-25-2014 06:10 AM
Exporting Resource Usage data to Excel samg54 Project 1 08-02-2013 05:28 AM
project 2010 resource usage runejors Project 1 04-04-2013 05:55 AM
MS Project - Resource usage printout scrinmemphis Project 1 02-22-2013 02:30 PM
Resource Usage sheet - options Andy Bain Project 1 11-05-2010 12:42 PM


All times are GMT -7. The time now is 07:41 PM.


Powered by vBulletin® Version 3.8.1
Copyright ©2000 - 2018, Jelsoft Enterprises Ltd.
SEO by vBSEO ©2011, Crawlability, Inc.
MSOfficeForums.com is not affiliated with Microsoft