Looking for a way to create a task field that would indicate if all predecessor tasks are complete. I would be most grateful for any help.

Thanks in advance,
Jay
Reply With Quote
  #2  
Old 10-10-2012, 03:03 AM
JulieS JulieS is offline Windows 7 64bit Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,696
JulieS will become famous soon enough
Default

See your other post at:
http://tek-tips.com/viewthread.cfm?qid=1695396
Reply With Quote
  #3  
Old 10-10-2012, 05:53 PM
jdove78 jdove78 is offline Windows 7 64bit Office 2010 64bit
Novice
 
Join Date: Oct 2012
Posts: 2
jdove78 is on a distinguished road
Default Thread continuing at Technet

http://social.technet.microsoft.com/...c-20f218c885bc
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Mail Merge Function not Noticing 'True' vs. 'False' Statement danellekent Mail Merge 1 04-27-2012 02:19 AM
excel cannot complete this task with available resources - vlookup Taisho Excel 4 01-27-2012 03:09 AM
On-screen indicator for overtype mode? carrfamily@mindspring.com Word 3 04-29-2011 01:56 PM
Next Page Indicator mkstreet PowerPoint 0 12-08-2010 11:36 PM
Stop the % Complete of subatasks from counting against the Main task bzeyger Project 0 06-08-2010 06:19 AM


All times are GMT -7. The time now is 09:41 AM.


Powered by vBulletin® Version 3.8.1
Copyright ©2000 - 2019, Jelsoft Enterprises Ltd.
SEO by vBSEO ©2011, Crawlability, Inc.
MSOfficeForums.com is not affiliated with Microsoft