cost loading of non scope items
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default cost loading of non scope items

Hello,
on one of the project schedules i am working on, they want to have not only the construction costs but also all other type of costs such as company overhead, design stage, procurement contingency etc distributed over time as well.

to approach this task do i just create independent activities called overhead or design for instance and enter them in to the schedule or do i need to create a separate summary schedule - this is going to upper management of that company so they only care about main distribution of costs over time, not how individual construction trades distribute

so as a result i need to include non work scope items into the schedule to show it together with the real construction scope items in the schedule.



how do i approach this situation?
Reply With Quote
  #2  
Old 08-24-2012, 05:28 AM
JulieS JulieS is offline cost loading of non scope items Windows 7 64bit cost loading of non scope items Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I would add separate "costing" tasks to the project as milestones and add the overhead costs to those milestones. You might add several milestones to help with the cost spread.

The design phase would be actual tasks as they do consume human resources.

Julie
Reply With Quote
  #3  
Old 08-24-2012, 05:50 AM
ketanco ketanco is offline cost loading of non scope items Windows 7 64bit cost loading of non scope items Office 2007
Expert
cost loading of non scope items
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

you said milestones but milestones have 0 duration. but they like to see these cost items distributed over time. so i would not do it as milestones but as activities right?

also, when i do this, they would inadvertently affect my % complete overall schedule. even if they arent part of my construction project, MS project will think it taht way. I guess there is no way to avoid it right?
Reply With Quote
  #4  
Old 08-24-2012, 05:55 AM
JulieS JulieS is offline cost loading of non scope items Windows 7 64bit cost loading of non scope items Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

As I said, add multiple milestones to spread the non-work costs out over time. As milestones have zero duration, they will not affect your project schedule. You will need to make sure you mark the milestone tasks as complete - but you can do that as you mark progress on your other tasks.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Which column shows just labor cost? ketanco Project 9 06-20-2012 02:19 PM
How to rename cost column ketanco Project 3 06-15-2012 03:06 PM
entering values for a cost type resource ketanco Project 3 12-26-2011 09:25 AM
File items not working in all Office's (save and loading) Sean5861 Office 0 10-02-2010 11:35 AM
Outlook 2007 Saved sent items list only holds the last ten items david.peake Outlook 0 06-01-2010 07:27 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:45 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft