I didn't save a baseline
 
Join Date: Jun 2012
Posts: 24
joday48 is on a distinguished road
Default I didn't save a baseline


Hi all

I didn't save a baseline in MS Project 2010 before I entered actual progress last week!

If I save one today and then enter this weeks progress will that be ok?

Also, do I need to set the status date to today before I enter any progress?

Thanks

Jo
Reply With Quote
  #2  
Old 06-29-2012, 05:44 AM
JulieS JulieS is offline I didn't save a baseline Windows 7 64bit I didn't save a baseline Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

If you save a baseline after tracking - the tracked data will be copied into the baseline fields -- so you will miss any variance against plan for those tasks.

If you need variance information (which most of us do), save either a full baseline now (before entering other progress) or a partial baseline if you don't have the fully developed plan.

I hope this helps

Julie
Reply With Quote
  #3  
Old 06-29-2012, 05:49 AM
joday48 joday48 is offline I didn't save a baseline Windows 7 64bit I didn't save a baseline Office 2010 32bit
Novice
I didn't save a baseline
 
Join Date: Jun 2012
Posts: 24
joday48 is on a distinguished road
Default

Hi Julie

Yes I need to look at variance. Will set a full baseline now.

Presume I need to set the status date (after setting the baseline) to today's date, and then enter the progress this afternoon?

Thanks for you're help Julie
Reply With Quote
  #4  
Old 06-29-2012, 08:14 AM
JulieS JulieS is offline I didn't save a baseline Windows 7 64bit I didn't save a baseline Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome. You would want to set the status date if you are using the Update Project command and tracking a large number of tasks in that way. The status date is also helpful to move incomplete work from the past forward to the status date.

I hope this helps.
Reply With Quote
  #5  
Old 07-05-2012, 12:24 AM
joday48 joday48 is offline I didn't save a baseline Windows 7 64bit I didn't save a baseline Office 2010 32bit
Novice
I didn't save a baseline
 
Join Date: Jun 2012
Posts: 24
joday48 is on a distinguished road
Default

Thanks Julie for your guidance
Reply With Quote
  #6  
Old 07-05-2012, 02:19 PM
JulieS JulieS is offline I didn't save a baseline Windows 7 64bit I didn't save a baseline Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're most welcome and thank you for the feedback.

Julie
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
I didn't save a baseline changing one activity in a baseline ketanco Project 5 02-11-2012 07:24 AM
some work was complete at my baseline ketanco Project 1 01-25-2012 02:45 PM
I didn't save a baseline Retrieve a baseline after it's been cleared fridos Project 2 05-11-2011 10:08 AM
I didn't save a baseline Help with Interim Baseline Variance poyns Project 1 05-27-2010 10:59 AM
Entourage (Mac) - is it possible to import if I didn't export? NJDevil Misc 0 01-19-2010 04:39 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:32 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft