#1
|
|||
|
|||
baseline duration, start and finsih dates
I am reviewing the schedule our contractor did and it has a baseline duration column, which shows durations. Then I wanted to see the baseline start and finish dates and inserted those columns but it says n/a in those columns for all activities. how is it possible that the activities in his schedule have baseline durations but not baseline start and finish dates? I checked the set baseline option and it doesnt say anything when baseline was saved so it means he didnt save basline correct? so then baseline start and finish dates showing n/a makes sense however why is there duration values for baseline durations then? |
#2
|
|||
|
|||
It sounds as though he may have just copied and pasted the duration to the baseline duration. When a baseline is saved automatically saved are:
Baseline Start Baseline Finish Baseline Duration Baseline Cost Baseline Work |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
baseline duration of summary not updating. why | ketanco | Project | 1 | 12-14-2011 09:07 AM |
duration vs actual start and finish dates | ketanco | Project | 1 | 12-14-2011 09:06 AM |
Task Start and End Dates | OTPM | Project | 2 | 12-04-2011 09:14 AM |
start-stop month dates in calendar | madison320 | Project | 0 | 06-24-2011 08:15 AM |
Setting Drop Dead Start Dates | greenboard | Project | 2 | 06-14-2010 08:12 AM |