some work was complete at my baseline
Hello at my baseline date, some of the activites were already complete to a certain extent. How can I reflect that in the baseline? I couldnt see any %baseline complete column. I want to say that at my baseline point, that activity was 60% complete for example
|
#2
|
|||
|
|||
There is no baseline % complete field. I'd just add a note to the task. If the task was started when you baselined then Baseline Start = Actual Start.
|
|