#1
|
|||
|
|||
Task duration between 2 fixed milestones
Hi,
in this simple senario M1--! ß---- task ---à! M2 M1 is a milestone, task is FS to M1 and M2 is a milestone fixed in time. How can I let the task duration ALWAYS be the duration between M1 and M2? I'd like to move M2 far in time and see the task duration getting larger. Thanks, /Stefano |
#2
|
|||
|
|||
Hello Stefano,
I believe you are looking for a hammock task. http://support.microsoft.com/kb/141733 I hope this helps. Julie |
#3
|
|||
|
|||
Exactly! Thanks a lot, I'm going to try it.
However it seems like a workaround, since I cannot connect the tasks to have a complete network diagram. I'll investigate. /Stefano |
#4
|
|||
|
|||
You're welcome. You are correct as the task has no predecessor or successor tasks, it will not fall "neatly" on the network diagram -- it will however appear without issue.
|
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
calculating duration | ketanco | Project | 5 | 12-15-2011 07:15 PM |
Duration does not change | caz46 | Project | 1 | 05-17-2011 07:51 AM |
Duration help (Quick question) | davy631 | Project | 3 | 03-07-2011 12:55 PM |
how to make the task starts next day if no time enough today(task can not be split) | duraid | Project | 1 | 10-25-2010 08:31 AM |
custom formula for duration | ericfons | Project | 0 | 03-23-2010 01:18 PM |