Old 01-23-2012, 07:24 AM
cettolox cettolox is offline Task duration between 2 fixed milestones Windows 7 64bit Task duration between 2 fixed milestones Office 2010 64bit
Novice
Task duration between 2 fixed milestones
 
Join Date: Jan 2012
Posts: 2
cettolox is on a distinguished road
Default Task duration between 2 fixed milestones

Hi,
in this simple senario



M1--!
ß---- task ---à!
M2
M1 is a milestone, task is FS to M1 and M2 is a milestone fixed in time. How can I let the task duration ALWAYS be the duration between M1 and M2?

I'd like to move M2 far in time and see the task duration getting larger.

Thanks,

/Stefano
Reply With Quote
  #2  
Old 01-23-2012, 12:39 PM
JulieS JulieS is offline Task duration between 2 fixed milestones Windows 7 64bit Task duration between 2 fixed milestones Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hello Stefano,

I believe you are looking for a hammock task.

http://support.microsoft.com/kb/141733

I hope this helps.

Julie
Reply With Quote
  #3  
Old 01-24-2012, 12:52 AM
cettolox cettolox is offline Task duration between 2 fixed milestones Windows 7 64bit Task duration between 2 fixed milestones Office 2010 64bit
Novice
Task duration between 2 fixed milestones
 
Join Date: Jan 2012
Posts: 2
cettolox is on a distinguished road
Default

Exactly! Thanks a lot, I'm going to try it.
However it seems like a workaround, since I cannot connect the tasks to have a complete network diagram. I'll investigate.

/Stefano
Reply With Quote
  #4  
Old 01-24-2012, 06:33 AM
JulieS JulieS is offline Task duration between 2 fixed milestones Windows 7 64bit Task duration between 2 fixed milestones Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome. You are correct as the task has no predecessor or successor tasks, it will not fall "neatly" on the network diagram -- it will however appear without issue.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Task duration between 2 fixed milestones calculating duration ketanco Project 5 12-15-2011 07:15 PM
Task duration between 2 fixed milestones Duration does not change caz46 Project 1 05-17-2011 07:51 AM
Task duration between 2 fixed milestones Duration help (Quick question) davy631 Project 3 03-07-2011 12:55 PM
how to make the task starts next day if no time enough today(task can not be split) duraid Project 1 10-25-2010 08:31 AM
custom formula for duration ericfons Project 0 03-23-2010 01:18 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:35 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft