weekend to monday logic problem
I'm writing a timeline sheet and need to know the formula if a timeline ends on a Saturday/sunday to default to the following Monday IE:
inspection deadline is 10 days ( not workdays) but if it ends on a weekend /holiday it needs to default to the following Monday. any help would be greatly appreciated |
#2
|
||||
|
||||
Suppose the initial date is in A1 and the deadline offset (the 10 days) is in B1. In that case, the inspection date could be calculated as:
=A1+B1+(MOD(A1+B1,7)<2)*(2-MOD(A1+B1,7))
__________________
Cheers, Paul Edstein [Fmr MS MVP - Word] |
#3
|
|||
|
|||
It worked with just a little customizing. Thanks a bunch
|
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Calculate time from midnight on (Weekend hours, Fri-Sat night shift problem) | stormrider2230 | Excel | 1 | 01-20-2016 01:41 PM |
force task start on monday | pascalbidouille | Project | 2 | 07-01-2015 01:57 PM |
'Monday to Friday' Date calculation help needed | ballst | Word | 10 | 12-16-2014 09:51 AM |
Weekend Working | Planner18 | Project | 1 | 10-29-2014 11:30 AM |
Calculating Weekend Allowance | WinIDS | Excel | 6 | 09-02-2011 01:27 AM |